MIL-P-53132(ME)
TEST PROCEDURES FOR 3kW POWER PLANT LOAD TRANSFER
Prior to performing the following procedures, ensure that the generator sets are in operating condition and properly serviced and that the "GND" terminal of the switchbox is connected to an earth ground.
1. The rotary switch of the switchbox shall be placed in the generator no. 1 position.
2. Start and operate the generators in accordance with the operator's manual at the rated load through the rotary switch for a minimum of 5 minutes. This test shall be performed at the load terminals of the switchbox.
3. At the conclusion of the generator no. 1 position test, the rotary switch shall be placed in the generator no. 2 position.
4. Repeat the test.
Inability of the switchbox assembly to maintain or transfer a rated load shall constitute failure of this test. Failure of the GFE generators to operate in accordance with the operator's manual shall not constitute failure of the test. The contracting officer shall be notified immediately of any such failure.