conform to 3.9.5. Inability to meet the requirements of 3.9.5 shall constitute failure of this test.
4.7.5.1 Road test. The first article power plant/power unit shall undergo 10 road cycles as defined in 6.14. The set shall be in operating condition and all fluids shall be at normal level, except the fuel tank shall be one-half fuel.
Each set shall be towed by an appropriate vehicle. TM 608.1 of MIL-STD-705, shall be conducted at the beginning of the test at the end of every two road cycles. These tests shall be conducted at rated load only. Prior to assembly and at the conclusion of the road test, the generator sets shall be subjected to an audio noise tests (see 4.6.2). Any rough handling damage (see 6.4.1), and
nonconformance to 3.9.5 shall constitute a failure.
4.8 Inspection of packaging.
4.8.1 First article pack inspection. The first article pack (see 6.7) shall be examined for the applicable defects listed in the quality assurance provisions of MIL-G-28554 and for the additional defects listed in 4.8.2.3 of this
specification. The presence of one or more defects shall be cause for rejecting the first article pack. Any defect(s) shall be corrected and the first article pack re-examined.
4.8.2 Quality conformance inspection of packaging.
4.8.2.1 Unit of product. For the purpose of inspection, a completed pack prepared for shipment shall be considered a unit of product.
4.8.2.2 Sampling. Sampling for examination shall be in accordance with
MIL-STD-105.
4.8.2.3 Examination. Sample power plants/power units, selected in accordance with 4.8.2.2, shall be examined for the applicable defects listed in the quality assurance provisions of MIL-G-28554 and the following defects. Presence of one or